Construction of Baltic Container Terminal Ltd. Additional Access Railway Tracks in Riga, Kundzinsala 1, on the Territory of Riga Free Port

Project completed: June 2011

Project Description

During the construction the following works were performed:

  • Construction of railway tracks (1145 m)
  • Installation of turnouts (3 pcs.)
  • Construction of subgrade
  • Construction of drainage system
  • Installation of point lighting system

Customer: Baltic Container Terminal Ltd.

1145 m

railway tracks

3 pcs.

turnouts