Construction of Optic Cable Line in Riga - Skulte Section (Vecaki - Carnikava - Saulkrasti - Skulte Station Open Lines)

Project completed: August 2021

Project Description

During the construction the following works were performed:

  • Laying of optic cable in ground (42 km)
  • Construction of cable canalization
  • Installation of optic panels and splice closures
  • Installation of manholes
  • Horizontal directional drilling

Customer: KATISS Ltd.

42 km

optic cable

5 psc.

manholes

Related projects

June 2022

Repairs of Alpha Ekspress Ltd. Railway Access Tracks №22 and №23 in Riga

Learn more

November 2020

Construction of Pedestrian Tunnel on Ogre Railway Station: Special Works

Learn more

December 2019

The 2-nd Stage of Development of Liepaja Port Railway Infrastructure

Learn more