Scroll down

Design and Construction of Railway Transport Branches for Riga Bulk Terminal (Senpasaule) Ltd. Terminal on Kundzinsala Island, Territory of Riga Free Port

Project completed: December 2014

Project Description

During the construction the following works were performed:

  • Construction of railway tracks (4 340 m)
  • Installation of turnouts (10 pcs.)
  • Construction of subgrade
  • Equipping of level crossing
  • Laying of railway signaling cables and installation of outdoor equipment
  • Installation of optic cable network
  • Erection of lighting masts (4 pcs.)
  • Construction of roads
  • Construction of drainage system, 1100 m long

Customer: Freeport of Riga Authority

4 340 m

railway tracks

10 pcs.

turnouts

Related projects

December 2018

Railway Construction for STREK Ltd. Terminal on the Territory of Riga Free Port, Krievu Island

Learn more

October 2018

The 2-nd Stage of Development of Liepaja Port Railway Infrastructure

Learn more

October 2018

Construction of Optic Cable Line in Riga - Skulte Section

Learn more
Load
more