Development of Railway Infrastructure for Neste-Statoil Ltd. Oil Terminal in Riga, Laivinieku str. 5, on the Territory of Riga Free Port

Project completed: August 2007

Project Description

During the construction the following works were performed:

  • Construction of railway tracks (1120 m)
  • Relocation of railway tracks (2870 m)
  • Dismantling and installation of turnouts (5 pcs.)
  • Construction of subgrade
  • Dismantling and installation of metal barrier (2040 m)
  • Dismantling and installation of lighting mast

Customers: Neste Latvija Ltd., Circle K Latvia Ltd.

3990 m

railway tracks

5 pcs.

turnouts