Modernisation of Centralized Post for Automatic Train Brake Charging and Running at Skirotava Wagon Maintenance Depot in Riga

Project completed: June 2005

Project Description

During the construction the following works were performed:

  • Installation of air duct for compressed air (1140 m)
  • Laying of communication cables (2730 m)
  • Installation of air intakes (2 pcs.)
  • Installation of brake charging and running facilities (2 pcs.)
  • Ground works

Customer: Latvian Railways SJSC

1140 m

airduct