Railway Construction for Bulk Cargo Transshipment Terminal in Ventspils Free Port

Project completed: December 2013

Project Description

The Railway Construction for Bulk Cargo Transshipment Terminal in Ventspils Free Port Project (2009-2013), co-financed by EU Cohesion Fund, provided for the construction of a new terminal for bulk cargo transshipment with berths and loading area in Ventspils Port, as well as the reconstruction of the existing and construction of new railway tracks to increase the volumes of reloaded timber and to ensure their loading from wagons directly on board the vessel.

 

Within the range of the Project the following works were performed:

  • Dismantling and construction of railway tracks (1909 m)
  • Installation of turnouts (4 pcs.)
  • Construction of drainage system
  • Laying of railway signaling cables
  • Equipping of turnouts with electric point machines

Customer: BMGS JSC

1909 m

railway tracks

4 pcs.

turnouts

Related projects

December 2018

Railway Construction for STREK Ltd. Terminal on the Territory of Riga Free Port, Krievu Island

Learn more

October 2018

The 2-nd Stage of Development of Liepaja Port Railway Infrastructure

Learn more

October 2018

Construction of Optic Cable Line in Riga - Skulte Section

Learn more
Load
more