Project Description
During the construction the following works were performed:
- Construction of railway tracks (4640 m)
- Installation of turnouts (12 pcs.)
- Construction of subgrade
- Construction of drainage system
- Installation of level crossing
- Construction of interlocking tower building
- Installation of the territory lighting
- Construction of external water supply and sewerage systems
- Installation of the yard relay and solid state interlocking
- Laying of power supply, signaling and tecommunications cable networks
- Construction of cable canalization
- Equipping of turnouts with electric point machines
- Construction of power substation
Customers: Freeport of Riga Authority, Euro Dzelzcelabuve Ltd.